An Order Scheduling Heuristic to Minimize the Total Collation Delays and the Makespan in High-Throughput Make-to-Order Manufacturing Systems

  • Husam Dauod
  • , Nieqing Cao
  • , Debiao Li
  • , Jaehee Kim
  • , Sang Won Yoon
  • , Daehan Won*
  • *Corresponding author for this work
  • State University of New York Binghamton University
  • Fuzhou University

Research output: Contribution to journalJournal articlepeer-review

Abstract

This paper presents an order scheduling heuristic to minimize the total collation delays and the makespan in high-throughput make-to-order manufacturing systems. Order collation delay is the completion time difference between the first and the last processed items within the same order. Large order collation delays contribute to a reduced throughput, non-recoverable productivity loss, or even system deadlocks. In manufacturing systems with high throughput, this scheduling problem becomes computationally expensive to solve because the number of orders is very large; thus, efficient constructive algorithms are needed. To minimize both objectives efficiently, this paper proposes a novel workload balance with single-item orders (WBSO) heuristic while considering machine flexibility. Through a comparison with (1) the non-dominated sorting genetic algorithm II (NSGA-II), (2) priority-based longest processing rule (LPT-P), (3) priority-based least total workload rule (LTW-P), and (4) multi-item orders first rule (MIOF), the effectiveness of the proposed method is evaluated. Experimental results for different scenarios indicate that the proposed WBSO heuristic provides 33% fewer collation delays and 6% more makespan on average when compared to the NSGA-II. The proposed method can work on both small and large problem sizes, and the results also show that for large size problems, the WBSO generates 74%, 89%, and 62% fewer collation delays on average than LPT-P, LTW-P, and MIOF rules respectively.

Original languageEnglish
Article number49
JournalOperations Research Forum
Volume4
Issue number2
DOIs
StatePublished - 2023.06

UN SDGs

This output contributes to the following UN Sustainable Development Goals (SDGs)

  1. SDG 9 - Industry, Innovation, and Infrastructure
    SDG 9 Industry, Innovation, and Infrastructure

Keywords

  • Make to order production
  • Order collation delays
  • Order scheduling
  • Parallel machines

Quacquarelli Symonds(QS) Subject Topics

  • Computer Science & Information Systems
  • Mathematics
  • Data Science
  • Economics & Econometrics

Fingerprint

Dive into the research topics of 'An Order Scheduling Heuristic to Minimize the Total Collation Delays and the Makespan in High-Throughput Make-to-Order Manufacturing Systems'. Together they form a unique fingerprint.

Cite this